Months after Pajaro flood, repair crews race against winter rain
Nearly six months after a Pajaro River levee breach upended the lives of about 3,000 Pajaro residents, the U.S. Army Corps of Engineers is trying to complete repairs on three parts of the levee before anticipated winter rain. Emergency repairs are expected to finish by the end of November but it could take longer if there is rain, said Holly Costa, emergency management chief for the Army Corps of Engineers. It is “very unusual” for levees to be fully repaired in the same year they were damaged, Costa said. When the levee was damaged in the past, “we didn’t get those repaired until two or three years afterwards,” she said. Completing the levee repairs before the rainy season is crucial because wet conditions could make the work difficult, Costa said.