City of SLO completes project to reduce flooding around Higuera Street
The City of San Luis Obispo celebrated the completion of its Mid-Higuera Bypass Project on Friday. The goal of the project was to reduce the risk of flooding in flood-prone areas around Higuera Street. Back in 2023, homes and businesses, like Nautical Bean and Abbey Carpet and Floor, located near High Street, were affected by flooding. … [T]he city installed two flood bypass channels, added 20-foot-wide channels, bench grading, and replaced the aging Bianchi Lane Bridge. All of this in hopes of increasing flood capacity by 40 percent during a 25-year storm event, reducing floodwater elevation by 6 to 18 inches, all while creating a healthy creek habitat.